Since 1998, Rotech Subsea has developed a reputable track record for many projects all over the world.

 

Task

Location

Client

Subsea Material

Water Depth

New Installations

 

 

 

 

 

Post Trenching 20” and 24” pipelines

Mexico

Horizon/Pemex

Firm Clay

80m

 

Post Trenching 36” and 24” pipelines

Mexico

Oceanografia

Firm Clay

35m

 

Post Trenching 20” pipeline

Mexico

Oceanografia

Firm Clay

40m

 

Post Trenching 12” pipelines

Venezuela

Z&P/ConocoPhillips 

Soft Mud

10m

 

Post Trenching 36” pipeline

Mexico

Oceanografia/Pemex

Firm Clay

40m

 

Post Trenching 20” pipeline

U.A.E.

COMACOE

Sandy Silt

5-21m

 

Post Trenching 16” pipeline

Mexico

Oceanografia

Firm Clay

50m

 

Post Trenching 12” pipeline

U.S. G.O.M

Chevron

Soft Clay

40m

 

Pipeline Crossings

Saudi Arabia

Global Industries                

Clayey Sand

9-36m

 

Post Trenching 12” pipelines

Venezuela

Z&P/ConocoPhilips

Soft Mud

5-25m

 

Post Trenching 16” pipelines

Mexico

Condux/Pemex

Firm Clay

33m

 

Post Trenching 8” pipelines

U.S. G.O.M

Con-Dive/Prime Offshore

Soft Clay

40m

 

Post Trenching 16” pipelines

Mexico

Condux/Pemex

Firm Clay

33m

 

Post Trenching 8” pipelines

U.S. G.O.M

Con-Dive/Prime Offshore

Soft Clay

40m

 

PreSweeping Sandwaves & 20” pipeline trenching

India

Global Ind./British Gas

Soft Sand and Clay 

25-40m

 

Post Trenching 24’ pipeline

Mexico

Condux/Pemex

Firm Clay

50m

 

Pipeline Post Trenching

Mexico

Condux/Pemex

Firm Clay

50m

 

Trenching 36” & 12” pipeline crossing

Mexico

Global Ind./Pemex

Sand and Mud

50m

 

Pipeline Trenching

U.S. G.O.M

Prime Offshore

Sand

46m

 

Post Trenching 12”, 24” & 36” pipelines

Mexico

Global Ind./Pemex

Sand and Clay                          

66m

 

Post Trenching 8” & 10” pipelines

U.S. G.O.M

Global Ind./Chevron

Soft Mud

65m

 

Post Trenching 36” Pipeline

Mexico

Oceanografia

Soft Mud

80m

 

Post Trenching 12” pipeline

U.S. G.O.M

Global Ind./Chevron

Soft Mud

70m

 

Spud Can Excavation

Vietnam

KNOC

Sand

5m

 

Pipeline Trenching

Mexico

Horizon

Soft Clay

60m

 

Pipeline Trenching

U.S. G.O.M

Global Ind/Devon

Soft Clay

40m

 

Pipeline Trenching

U.S. G.O.M

Global Ind/Apache

Firm Clay

25m

 

Post Trenching 24” pipelines

Mexico

Horizon

Soft Clay

80m    

 

Post Trenching pipeline

Mexico

Condux/Pemex

Soft Clay

45m-65m

 

Post Trenching pipeline                                          

Mexico

Condux/Pemex

Soft Clay

45-65m

 

Post Trenching 12” pipeline

U.S. G.O.M

Global Ind./ElPaso

Soft Clay

15m

 

Pipeline Trenching

Trinidad

Acergy

Soft Mud

75m

 

Post trenching 12”, 18” & 20” pipelines

Mexico

Global Ind. /Pemex

Firm clay

40m-55m

 

Pipeline crossing preparation

Mexico

Condux/Pemex

Firm clay

50m

 

Pipeline trenching and crossing preparation          

Mexico

Condux/Pemex

Firm clay

40m-60m

 

Pipeline trenching 30” pipeline

Mexico

Condux/Pemex

Clay

45m

 

Post trenching of a 20” pipeline

Mexico

Global Ind. /Pemex

Firm clay

40-55m

 

Post trenching 30” pipeline

Mexico

Condux/Pemex

Clay

45

 

Post trenching 11” pipeline

Mexico

Global Ind. /Pemex

Clay

20m-30m

 

Post trenching 10” pipeline

Mexico

Condux/Pemex

Clay

20m-30m

 

Post trenching of a 10” pipeline

Mexico

Global Ind. /Pemex

Firm clay

50m

 

Post trenching 10” pipeline

Mexico

Condux/Pemex

Clay

20m-30m

 

Post trenching 11” pipeline

Mexico

Global Ind. /Pemex

Clay

20m-30m

 

Post trenching 10” pipeline

Mexico

Global Ind. /Pemex

Clay

50m

 

Pre-trenching

Israel

Desalination CP

Sand

7m-15m

 

Post trenching 2 x 12" pipelines

India

Clough/Niko

Stiff clay

4m - 20m

 

Post trenching 12" pipleine

India

Clough/Niko

Firm clay

2m - 5m

 

Post trenching 8" pipeline

Mexico

Global Ind. /Pemex

Firm clay

40 - 50 m

 

Post trenching 24" pipeline

Mexico

Global Ind. /Pemex

Firm clay

40m - 50m

 

Post trenching 20" pipeline

Indonesia

Saipem/Total

Firm clay

5m-10m

 

Numerous 8” – 6” crossings

Mexico

Global Ind. /Pemex

Firm clay

38m-55m

 

Post trenching 20” & 24” pipelines

Mexico

Global Ind. /Pemex

Firm clay

40m-50m

 

Seabed preparation for jack-up rig spud cans

Bay of Bengal

IEV/Premier Oil

Sand

100m

 

Pipeline trenching

Mexico

Global Ind. /Pemex

Firm Clay

40m-60m

 

Post trenching 600m of 24" pipeline in clay

Indonesia

J Ray McDermott

Stiff clay

5m

 

Post trenching 216m shore approach  of 30" pipeline

Cameroon

Global Industries

Sand and clay

3m-8m

 

Post trenching various pipelines & umbilicals

Egypt

Stolt Offshore

Sand and clay

8m-20m

 

Post trenching of various sized pipelines

Egypt

Stolt Offshore

Sand with no cohesion

2m-10m

 

Seabed preparation for jack-up rig spud cans

Bay of Bengal

Premier Oil

Sand

100m

 

Pipeline Trenching

Mexico

Global Industries

Clay

40m-60m

 

Seabed preparation for Jacket installation

East Timor Sea

J Ray McDermott

Sands and clay

85m

 

Backfilling of 45km trench

Mexico

Horizon

Sands and clay

40m-60m

 

Post trenching 9km of various sized pipelines

Mexico

Horizon

Sands and clay

40m-60m

 

Post trenching various sized pipelines

Egypt

Stolt Offshore

Sand with no cohesion

2-8m

 

Post-trenching 70km of 36" pipeline - continued

Egypt

GUPCO/BP

Sands and light clay

5m-65m

 

Post-trenching 70km of 36" pipeline

Egypt

GUPCO/BP

Sands and light clay

5m-65m

 

Seabed preparation for rock dumping

Wales

Balfour Beattie/Bechtel

Silts and clay

10m

Inspection, Maintenance & Repairs

 

 

 

 

 

Valve Cover Clearance

U.S. G.O.M

Chet Morrison Contractors

Soft Clay

50m

 

Pipeline Deburial

North Sea

Acergy/BP

Soft Clay

30m

 

Pipeline Deburial

U.S. G.O.M

Chevron

Firm Clay

20m

 

Pipeline Deburial

U.S. G.O.M

Chevron

Firm Clay

20m

 

Pipeline Trenching for repair

U.S. G.O.M

BP

Soft Mud

187m

 

Pipeline Trenching for repair

U.S. G.O.M

Onyx/Enterprise

Soft Mud     

230m

 

Pipeline Trenching for repair

U.S. G.O.M

BP

Soft Mud                        

200m

 

Pipeline deburial

U.S. G.O.M

Oceaneering/Chevron

Mud

220m

 

Post trenching of a 30” pipeline

U.S. G.O.M

CHET/SNG

Compacted Sand/Clay

3m

 

Post Hurricane Pipeline Repair

U.S. G.O.M

Oceaneering/Shell

Mud

1000m

 

Post Hurricane Repair Work

U.S. G.O.M

Global Ind/Chevron

Mud

10m

 

Post Trenching 44” pipeline

U.S. G.O.M

Chet Morrison/BP

Sand

3m – 6m

 

Post Hurricane Repair Work

U.S. G.O.M

Global Ind/Chevron

Mud

20m – 40m

 

Deburial of 32" & 24" pipelines for inspection

UK, North Sea

Subsea7/Total

Rock dump removal

110m

 

Pipeline Deburial

UK, North Sea

Allseas

Sand

15m-25m

 

Seabed preparation & post trenching 24” pipeline

Egypt

Stolt/Burullus

Sand & soft clay

12m-40m

 

Seabed Preparation for habitat installation

North Sea

Allseas

Sand & soft clay

45m

 

Deburial of a pipeline

U.S. G.O.M

Global Ind. /Chevron Texaco  

Sand

210m

 

Pipeline Deburial

U.S. G.O.M

Global Ind. /Chevron Texaco  

Mud

40m-60m

 

Pipeline deburial

U.S. G.O.M

Cal Dive/Williams

Mud

290m

 

Pipeline deburial

U.S. G.O.M

Oceaneering

Mud

75m

 

Freespan Correction

Gulf of Thailand

Global Industries

Mud waves

80m

 

Deburial of mine outfall pipes and area clearance

N E Coast of England

Briggs Marine

Silt

14m

Salvages/Decommissioning

 

 

 

 

 

Platform Salvage Excavation

U.S. G.O.M

Howard Energy

Soft Clay

70m

 

Platform Leg Excavation

U.S. G.O.M

Con-Dive/ENI

Soft/Medium Clay

70m

 

Jacket Leg Excavations

U.S. G.O.M

Chet Morrison Contractors

Soft Clay

50m

 

Platform Salvage/Well Excavations

U.S. G.O.M

Chevron

Soft/Firm Clay

40m

 

Conductor Excavation

U.S. G.O.M

Tetra Technologies

Soft Mud

70m

 

Conductor Excavation

U.S. G.O.M

Tetra Technologies

Soft Clay

30m

 

Well-Head and Jacket Leg Excavation

U.S. G.O.M

Newfield Exploration

Soft Clay

32m

 

Well-Head Excavation

U.S. G.O.M

Newfield Exploration

Firm Clay

30m

 

Backfilling Well Excavation

U.S. G.O.M

Magnum Hunter

Soft Mud

50m

 

Well-Head Excavation

U.S. G.O.M

Magnum Hunter

Soft Mud

50m

 

Well-Head Excavation

U.S. G.O.M

Newfield Exploration

Firm Clay

30m

 

Well-Head Excavation

U.S. G.O.M

Magnum Hunter                      

Stiff Clay        

45m

 

Rock dump removal

Sakhalin, Russia

Jan de Nul/Saipem

Large & small rocks

30m

 

Jacket Leg Excavations - Decommissioning

U.S. G.O.M

Cal Dive/Anadarko               

Mud

70m

 

Post Hurricane Conductor Deburial

U.S. G.O.M

BP

Mud

40m

 

Jacket Leg Excavations – Decommissioning

Indonesia

IEV/Shell

Sand & soft clay

85m

 

Jack-up rig leg recovery

U.S. G.O.M

Titan/Ensco

Stiff Clay

110m

 

Excavation within Jack-up legs

Dutch, North Sea

Noble Drilling

Sand and clay

50m-60m

 

Providing access for hydraulic pipeline cutter

Singapore

Van Oord

Rock & Backfill removal

20m

 

De-burial of Jack-up spud cans

Dutch, North Sea

Noble Drilling

Sands to stiff clay

50m-60m

 

Well-head deburial

Malaysia

Shell

Sands and light clay

80m

Tie-Ins

 

 

 

 

 

Well-head deburial

Malaysia

Shell

Sands and light clay

80m

 

Subsea Tie-In Excavation

U.S. G.O.M

Con-Dive/NNG

Soft Mud

55m

 

Trench Clearing/Rock Dump Removal

Sakhalin

Saipem

Sandy Sediment

35m

 

Subsea Tie In Trenching 

U.S. G.O.M

Horizon

Firm Clay

30m

 

Subsea Tie In/8” Pipeline Deburial

U.S. G.O.M

BP

Soft Clay

210m

 

Pipeline deburial

North Sea

Subsea7/Total

Sand

110m

 

Pre & Post trenching

Sakhalin, Russia

Jan De Nul/Saipem

Sand

10m - 30m

 

Rock Dump removal 300 - 400 mm

W Australia

Technip-Subsea 7/Woodside

Rock dump removal

125m

 

Rock Dump Removal for pipeline deburial

UK, North Sea

Subsea 7/Total

Rock dump removal

100m - 110m

 

Seabed preparation for tie in installation

UK, North Sea

Subsea 7/Total

Sands & very soft clay

43m

 

Post trenching of two pipelines

North Sea

Subsea 7/Total

Sand

2m-5m

Cable Burial

 

 

 

 

 

Cable burial

North Sea

Van Oord

Sand

2m-5m

 

Pre-trenching cable

Mexico

Demar/Pemex

Firm clay

30m-55m

 

Pre-trenching cable

Mexico

Demar/Pemex

Firm clay

30m-55m

 

Post trenching 200 mm cable

UK, North Sea

Cns/Vestas/Van Oord

Soft clay

8m - 15 m

 

Post trenching 1.1km of 6" fibre-optic conduit

Scotland

Stolt Offshore

Sands and light clay

2m-10m

 

Post trenching of 400m of 35mm fibre-optic cable

Scotland

Stolt Offshore

Sands and light clay

10m-15m

Harbour Clearance

 

 

 

 

 

Berth Clearance

Scotland

Montrose Harbour

Mud/Silt

4m-8m

 

Jetty Clearance – multiple

Indonesia

Caltex

Silt/Mud

11m-20m

 

Jetty Clearance – Decommissioning

Azerbaijan

Technip

Silt, Mud & Soft Clay

4m – 6m

 

Harbour clearance

Scotland

Montrose Harbour

Silt

5m